Touréchaf

56 NT008 - TOURÉCHAF TECHNICAL INFORMATION T O U R É C H A F : F A L S E W O R K T O W E R W I T H I N T E G R A L S A F E T Y S Y S T E M Lifting and transport... WARNING: The whole must be firmly strapped to avoid any risk of shedding during transport.Wedging where the straps are, is recommended.The bottom diagonal braces are assembled at the inside to avoid damages. 30° max. Lifting: Use the rings of the plates to lift the Pylons. Transport: It is possible to deliver Pylons assembled on the site. M12-110 Bolt S C R E W J A C K R E T A I N I N G D E V I C E 30° max. WARNING: Before lifting, ensure that the screw jack retaining device is in place. Lifting must be performed with 4 slings of equal length and which form a max. angle. of 30° with respect to the vertical. WLL of the ring: 4 tonnes. Standards assembly tensile strength : 1,25 tonnes.