55 NT008 - TOURÉCHAF TECHNICAL INFORMATION T O U R É C H A F : F A L S E W O R K T O W E R W I T H I N T E G R A L S A F E T Y S Y S T E M > 8 - Lift the Pylon via the rings provided for this purpose. Location for the lifting rings. > 6 - Position the 4 head ledgers. Rotation of the legs is blocked. > 7 - Assemble the screw jacks on the head and footplates. Fit the bolts on the screw jacks for the lifting (anti-dislocation). WARNING: General lifting rules must be followed. Bolt M12-110 TOURÉCHAF