31 NT008 - TOURÉCHAF TECHNICAL INFORMATION T O U R É C H A F : F A L S E W O R K T O W E R W I T H I N T E G R A L S A F E T Y S Y S T E M > Falsework blocks installed on the dome of a reservoir: Prefabrication of falsework block on the ground on a temporary scaffolding structure, before the cranage thereof 50 m high. Several tools are placed side by side under the girder. Stability rule for the assembly and dismantling phases of the tower: The scaffolding is set to reproduce the shape of dome. In the falsework position: > Single falsework tower equipped with stabilisers: In the moving position: Screw jacks in contact Raised screw jacks h < 6.00 m H < 3 L min. L The stabilizers comprise scaffolding standards, ledgers and diagonal braces. > Rolling tool for the girder formwork: TOURÉCHAF