MILLS FORMWORK
M I L L S P A N O : C O M P L E T E H O R I Z O N T A L F O R M W O R K S Y S T E M NT 009 - MILLS FORMWORK TECHNICAL INFORMATION Dismantling ... 17 > 1 - Remove the bolts between decks. Unscrew all the screw-jack heads. Install rollers on the fork heads (see page "Accessories"). > 2 - For the safety of the workers, a lifeline will be set up along the bridge deck.Then, remove the plywood boards as the removal takes place. > 4 - Use the crane to remove the deck. On the ground, remove the last plywood and the guardrails. > 3 - As soon as possible, anchor the slings of the crane, provided with 4 5T lifting rings of the Artéon type, at the locations provided for this purpose on the deck. The centre of gravity of the deck must not get close to the last row of fork heads. If a machine is used to move the decks, the slings have to be fastened on the ends of the string beams of the decks via a pin placed in the Ø23 hole (e.g.: HM20-130 bolt). ASTUCE 3 0 ° m a x . FORMWORK