E S C A L I B M I L L S : S I T E S P I R A L S T A I R T O W E R W I T H 7 WARNING: The erection guardrail must not be used as a substitute for the barrier gate. > 6 - Install and fix the barrier gate: the erection guardrail is in the horizontal position. > 7 - With slings attached to the 2 lifting rings, the topmost module is fitted. Bolt the 4 standards together using M24 screws. > 9 - At the access levels, the rails are positioned so as to privilege access by the main side A (side names shown on the sticker). > 8 - Check that the stair tower has been anchored before unhooking the slings. Swing the guardrails swung out of the way to allow access to the required level. TIP 210mm The last step used should ideally be placed 210mm lower than the slab being serviced. “T OPMOST ” MODULE ESCALIB MILLS NT 010 - ESCALIB MILLS TECHNICAL INFORMATION